Project:
Mercury Blvd.
Location: Hampton, VA
Client: Henry S. Branscome, Inc.
Contract Value: $3,500,000
Description: Construct three new bridges on Mercury Blvd. - Mercury Blvd.
over Newmarket Creek, Northbound LaSalle Ave. over Mercury Blvd., Southbound
LaSalle Ave. over Mercury Blvd.
Work Performed:
· Dismantled and removed existing bridges
· Foundation pile driving
· Placed footing, pier, abutment, retaining wall, approach slab, and bridge
deck concrete
· Installed structural steel and precast concrete girders
· Designed and constructed all concrete forms and temporary falsework |
|